Independent Assurance, Peer Review, pre-FID
Subsurface & Reservoir, Subsea Discipline Engineers, Front End Development Engineers, Technical Safety, Project Services, Project Managers
Offshore Brazil
Advisory
Infinity carried out an independent, owner-side assurance review of an offshore Brazilian development ahead of sanction, working across the subsurface and the facilities together — reservoir basis, development plan, subsea system, safety case and environmental consent — and issuing a formal review report to the operator.
The operator was preparing to develop an accumulation tied back to an existing production facility and needed independent confirmation that the development plan was robust before committing. Infinity were given access to the full development data set and worked through it as a single assurance exercise rather than a series of discipline checks. Critically, that included the subsurface: the static model, the reservoir management plan and the production profiles underpinning the development were reviewed alongside the facilities design rather than taken as a fixed input. The review also covered the executive development plan, the safety case and the environmental impact assessments for both the new accumulation and the host field, and ran alongside a structured clarification process with the operator’s subsurface and project teams.
Infinity sit deliberately at the join between subsurface and facilities, which is where most development value is won or lost and where neither a pure reservoir consultancy nor a pure engineering house is positioned to look. On this review that meant testing the production profiles and the facilities design against each other rather than in sequence. Infinity worked as an extension of the operator’s own team rather than as a remote reviewer, running a live clarification process across almost sixty separate queries. Infinity also revised the operator’s project risk register directly, so the review left the project with an improved control document rather than only a list of comments.
The operator received a formally issued assurance report, taken through two revisions, together with a revised risk register and a set of design optimisation recommendations. The review gave the board independent confirmation of the development basis at the point of sanction.